- IATA code
- LTH
- Location
- Long Thành area, Đồng Nai province (post-2025 boundaries), about 40 km east of HCMC
- Status (23 Nov 2026)
- Not yet open; trial operations under way
- Planned opening
- 00:00, 24 December 2026 (ACV)
- Phase 1 capacity
- 25 million passengers a year, one terminal, one 4,000 m runway
- Long-haul switch
- Planned from 28 March 2027
As of 23 November 2026, Long Thành International Airport is not yet in commercial service. The operator, the Airports Corporation of Vietnam (ACV), has set the start of commercial operations for 00:00 on 24 December 2026, after earlier targets of June, September and 1 December 2026 slipped. Trial operations are under way and the first official test flight landed in December 2025.
For travellers, nothing changes overnight. The opening phase is small, about 20–30 flights a day, and Tân Sơn Nhất (SGN) keeps handling the vast majority of flights. The big shift comes in 2027, when long-haul and then most other international flights are planned to move to Long Thành. The key habit to build now: always check which airport is printed on your ticket.
Where is Long Thành airport?
The airport is in the Long Thành area of Đồng Nai province (post-2025 boundaries), about 40 km east of central Ho Chi Minh City, beyond Thủ Đức and the Đồng Nai River. The first phase has one passenger terminal designed for 25 million passengers a year and one 4,000 m runway, with further phases planned later.
Unlike Tân Sơn Nhất, which is surrounded by the city, Long Thành sits next to the HCMC–Long Thành–Dầu Giây expressway, so the journey time depends far more on how quickly you reach the expressway than on the distance itself.
Timeline
| Date | Milestone |
|---|---|
| Dec 2025 | First official flight lands (calibration and trial phase) |
| 2026 | Commercial opening targets move from June to September, then 1 December |
| 30 Oct and 19 Nov 2026 | ACV sets commercial start for 00:00, 24 December 2026 |
| 24 Dec 2026 – end Mar 2027 | Phase 1: about 20–30 flights a day using the terminal’s west wing |
| 28 Mar 2027 (summer schedule) | Long-haul international passenger and cargo flights planned to move to Long Thành |
| 30 Oct 2027 (winter schedule) | Nearly all other international flights planned to follow, except Vietnamese airlines’ routes under 1,000 km |
These are plans announced by ACV and the aviation authority. Dates have moved several times, so treat everything after December 2026 as provisional.
Which flights will use Long Thành first?
According to the plan reported on 19 November 2026, the opening phase includes Vietnam Airlines international flights to Beijing, Guangzhou, Hong Kong and Manila (44 a week), Vietnam Airlines flights to Hanoi, and Vietjet flights to Hanoi, Hải Phòng, Vinh, Thanh Hóa and Đà Nẵng. Reports disagree on the total weekly cap (one says 226 flights a week, another 366). The official schedule was due to be published in early December 2026.
Foreign airlines are planning their own moves: Tuổi Trẻ reported on 18 November 2026 that 24 international airlines intend to switch to Long Thành from late 2027.
Check your ticketIf your booking shows LTH or “Long Thành”, you are not flying from Tân Sơn Nhất. Allow far more time to get to the airport, and do not assume connections between the two airports are quick.
How will you get there?
- By road: the HCMC–Long Thành–Dầu Giây expressway is the main link. Further roads (part of the Biên Hòa–Vũng Tàu expressway, a section of Ring Road 3 and local roads 25B and 25C) were targeted to open around the same time as the airport.
- Ride-hailing and taxis: expect Grab, Xanh SM and taxis to serve the airport as they do at SGN; fares will be much higher than the short hop from Tân Sơn Nhất to District 1 because of the distance.
- Buses: ACV and the city have discussed 24/7 buses and a direct shuttle between Tân Sơn Nhất and Long Thành, and a 13-route bus plan was drawn up with two express routes in the first phase, including one from the Saigon bus station. As of late October 2026 no timetable had been published.
- Rail: there is no rail link at opening. A Thủ Thiêm–Long Thành light-rail line and the North–South high-speed railway are planned for the future, as is a proposed extension of Metro Line 1 towards Long Thành.
What it means for travellers
- Until March 2027, almost all international and domestic flights still use Tân Sơn Nhất. Read our Tân Sơn Nhất guide.
- From the 2027 summer schedule, long-haul flights (Europe, Australia, the Gulf, North America) are expected to start moving. Check your direct flight options and the departure airport on your booking.
- Connections: a self-transfer between Long Thành and Tân Sơn Nhất means a long road trip; allow several hours and avoid tight separate-ticket connections.
- Where to stay: if you have an early flight from Long Thành, staying on the eastern side of the city (Thủ Đức, Thảo Điền) cuts the journey; see where to stay.
- Tân Sơn Nhất is not closing. It remains the city’s domestic hub and will keep many regional international flights.
Frequently asked questions
Is Long Thành airport open?
Not as of 23 November 2026. ACV has scheduled commercial operations to start at 00:00 on 24 December 2026.
How far is Long Thành airport from Ho Chi Minh City?
About 40 km east of the city centre, in Đồng Nai province, reached mainly by the HCMC–Long Thành–Dầu Giây expressway.
Will Tân Sơn Nhất close when Long Thành opens?
No. Tân Sơn Nhất continues to operate; international flights are planned to move to Long Thành in stages during 2027.
Which airlines fly from Long Thành first?
The opening plan includes Vietnam Airlines (Beijing, Guangzhou, Hong Kong, Manila, Hanoi) and Vietjet (Hanoi, Hải Phòng, Vinh, Thanh Hóa, Đà Nẵng). The official schedule was due in early December 2026.
Is there a train or metro to Long Thành airport?
Not at opening. Rail links are planned but not yet built; access is by road.
Sources
- Tuổi Trẻ — Long Thành to operate from 24 Dec with 20–30 flights a day (19 Nov 2026) (checked 2026-11-23)
- CafeF — commercial operations expected from 24 Dec (30 Oct 2026) (checked 2026-11-23)
- Vietnam News — three-stage transition plan (Jul 2026) (checked 2026-11-23)
- Tuổi Trẻ — 24 foreign airlines plan to switch from late 2027 (18 Nov 2026) (checked 2026-11-23)
- Tuổi Trẻ — first official flight lands (Dec 2025) (checked 2026-11-23)
- CafeF — connections between HCMC and Long Thành (27 Oct 2026) (checked 2026-11-23)
- VietnamPlus — bus network plan for Long Thành and Tân Sơn Nhất (checked 2026-11-23)
- Wikipedia — Long Thành International Airport (checked 2026-11-23)